E-News Update - Fall 2019

 

Construction Authority Awards Design-Build Contract to Kiewit-Parsons to Build Glendora to Montclair Extension

In August, the Construction Authority Board of Directors awarded the main design-build
contract to Kiewit-Parsons, a Joint Venture, for the Foothill Gold Line light rail extension from
Glendora to Montclair. The awarded design-build contract includes an $805.6 million base
scope for the first nine miles of the project from Glendora to Pomona, with a two-year contract
option to complete the full 12.3-mile project to Montclair for a total contract award of $1,186.9
million if additional funds are secured by September 2021. The base scope includes all elements
of design and construction for the first nine-mile segment, including relocation of the existing
freight track, installation of the light rail track system, four new light rail stations (in Glendora,
San Dimas, La Verne and Pomona), improvements at 40 grade crossings (nearly half with new or
renovated bridges) and much more. The contract option would extend the work of the design-
build team to complete the full 12.3-mile project to Montclair and add stations in Claremont
and Montclair.

The final proposal by Kiewit-Parsons was deemed the best value for the agency following a
nearly two-year procurement process. Their final proposal resulted in the team being ranked
highest in all technical evaluation categories, and provided the lowest bid price based on the
formula set out in the request for proposals for the base scope to Pomona and contract option
to Montclair.

Kiewit and Parsons have teamed up dozens of times to complete design-build projects,
including successfully building the first two segments of the Foothill Gold Line project which
were completed on time and under budget in 2003 and 2015 respectively. They have designed
and built hundreds of major infrastructure projects, and both are award-winning companies,
providing world-renowned experience.

With the contract awarded, the project will begin major construction in 2020 and be completed
to Pomona in 2025, and to Montclair in 2028 if the contract option is activated.

 

For more information about this important transportation project visit www.foothillgoldline.org.